PRESUPUESTO DE VENTAS
Lizzikatiuska30 de Julio de 2014
445 Palabras (2 Páginas)226 Visitas
PASO 1 PRESUPUESTO DE VENTAS
SEMESTRE CONCEPTO PRECIO DE VTA. UNIDADES SUMA TOTAL
1er SEM ROSAS S/. 65.00 450 S/. 29,250.00 S/. 48,589.00
ORQUIDIAS 83.00 233 19,339.00
2do SEM. ROSAS 65.00 356 23,140.00 45,965.00
ORQUIDIAS 83.00 275 22,825.00
TOTAL S/. 94,554.00
PASO 2 PRESUPUESTO DE UNIDADES A PRODUCIR
CONCEPTO ROSAS ORQUIDIAS
1er SEM 2do SEM. 1er SEM 2do SEM.
VENTAS 450 356 233 275
(+) INV.FINAL 300 400 400 300
(=) VTAS DESEADAS 750 756 633 575
(-) INV. INICIAL 300 300 400 400
(=) UNIDADES A PRODUCIR 450 456 233 175
PASO 3 PRESUPUESTO DE REQUERIMIENTO DE MATERIA PRIMA
PERIODO CONCEPTO BASES FOLLAJES
1er SEM. ROSAS 1935 9000
ORQUIDIAS 419.4 3,495.00
SUMAS 2,354.40 12,495.00
2do SEM. ROSAS 1,960.80 9,120.00
ORQUIDIAS 315.00 2,625.00
SUMAS 2,275.80 11,745.00
TOTALES 4,630.20 24,240.00
COSTO DE MAT. PRIMA S/. 162,057.00 S/. 363,600.00 S/. 525,657.00
PASO 4 PRESUPUESTO DE COMPRA DE MATERIA PRIMA
BASES FOLLAJES
CONCEPTO 1er. Sem 2do. sem. 1er. Sem 2do. sem.
UNIDADES A PRODUCIR 2354.4 2275.8 12495 11745
(+) INV. FINAL 500 600 200 500
(=) DISP. DE MAT. PRIMA 2,854.40 2,875.80 12,695.00 12,245.00
(-) INV. INICIAL 500 500 200 200
(=) COMPRA DE MAT. PRIMA 2,354.40 2,375.80 12,495.00 12,045.00
(X) COSTO 35 35 15 15
(=) COSTO DE CAMPRA S/. 82,404.00 S/. 83,153.00 S/. 187,425.00 S/. 180,675.00 S/. 533,657.00
PASO 5 PRESUPUESTO DE MANO DE OBRA
CONCEPTO PRODUC. REQ. HORAS REQ. TOTAL COSTO CONSUMO
ROSAS 450.00 5 2,250.00 8.50 19,125.00
456.00 5 2,280.00 8.50 19,380.00
ORQUIDIAS 233.00 9 2,097.00 8.50 17,824.50
175.00 9 1,575.00 8.50 13,387.50
8202 S/. 69,717.00
1er. Sem 36,949.50
2do. sem. 32,767.50
PASO 6 PRESUPUESTO DE GTOS IND. DE FABRICACION PASO 7 PRESUPUESTO DE GATOS DE VTAS Y ADM
CONCEPTO IMPORTE CONCEPTO IMPORTE
DEPRECIACION 50 VARIOS 42
AGUA 25 TARJETAS 12
PLASTICO 9 GLOBOS 6
VARIOS 8 LISTON 5
TOTAL DE GTOS DE FAB. IND. 92 TOTAL 65
G.I.F 92 0.01
TOTAL DE HRS. 8202
PASO 8 PRESUPUESTO DE INVENTAROS FINALES
CTO. X UNIDAD ROSAS CTO. X UNIDAD ORQUIDIAS
BASES 4.3 35 150.5 1.8 35 63
FOLLAJES 20 15 300 15 15 225
MANO DE OBRA 5 8.5 42.5 9 8.5 24
GTOS. IND. FABRICACION 5 0.01 0.06 9 0.01 0.08
493.06 312.08
BASES 600 35 = S/. 21,000.00 S/. 28,500.00
FOLLAJES 500 15 = S/. 7,500.00
ROSAS 400 493.06 = S/. 197,222.43 S/. 290,845.68
ORQUIDIAS 300 312.08 = S/. 93,623.25
PASO 9 PRESUPUESRO DE COSTO DE VENTAS
CONCEPTO 1ER.SEM 2DO.SEM TOTAL
MAT. PRIMA REQ. 162,057.00 363,600.00 S/. 525,657.00
MANO DE OBRA 36,949.50 32,767.50 69,717.00
...