Granulometria. PRESUPUESTO GENERAL
Rosa Miriam Baca SabaApuntes14 de Marzo de 2019
1.989 Palabras (8 Páginas)113 Visitas
“AÑO DE LA INTEGRACIÓN NACIONAL Y ELRECONOCIMIENTO DE NUESTRA DIVERSIDAD”
[pic 1]
TEMA:
“PRESUPUESTO” TRABAJO FINAL
ALUMNO :
FERRER LAVADO, Williams
DOCENTE:
ING.BERECHE CARDENAZ, Ronald
MATERIA:
INTRODUCCION ALA INGENIERIA
FACULTAD:
INGENIERIA
ESCUELA:
CIVIL
CICLO :
I – 2012
SECCION :
“D”- turno tarde
PIURA-2012
PRESUPUESTO GENERAL | ||
1 | PERSONAL | |
2 | ELEMENTOS ESTRUCTURALES | |
2.1 | ZAPATAS | |
2.2 | COLUMNAS | |
2.3 | VIGAS | |
3 | ENCOFRADOS | |
3.1 | E. de TECHO | |
3.2 | E. de VIGAS | |
3.3 | E. de COLUMNAS | |
4 | PAREDES | |
4.1 |
| LADRILLOS |
4.2 |
| FRAGUADO |
4.3 |
| EMPASTADO |
5 | TECHO ALIGERADO | |
6 | PORCENTAJES DE DESPERDICIOS | |
6.1 | CONCRETO | |
6.2 | MORTEROS | |
6.3 | LADRILLOS | |
7 | ACCESORIOS | |
7.1 |
| PUERTAS |
7.2 | VENTANAS |
MATERIALES COMERCIALES | |||
PCH | PIEDRA CHANCADA | M3 | S/. 60 |
AG | ARENA GRUESA | M3 | S/. 25 |
CA | CEMENTO AZUL | BLS | S/. 22.10 |
AF | ARENA FINA | M3 | S/. 40 |
CR | CEMENTO ROJO | BLS | S/. 21.10 |
LM | LADRILLO M | MX | S/. 300 |
LT | LADRILLO DE TECHO | UE | S/. 1.80 |
AG | ARENA GRUESA | M3 | S/. 4,000 |
VENTANAS | EA | S/. 180 | |
PUERTAS INTERIORES | EA | S/. 160 | |
PUERTAS EXTERIORES | EA | S/. 210 |
DESARROLLO
- PERSONAL:
EQUIPO DE TRABAJO | P.Diario | PERS. | TIEMPO | |||
INGENIERO | EFE (S/.) | 333.33 | 1 | 240 días | 80000 | |
MAESTRO | EFE(S/.) | 100.00 | 1 | 240 días | 24000 | |
OFICIAL | EFE(S/.) | 80.00 | 3 | 240 días | 57600 | |
OBRERO | EFE(S/.) | 60.00 | 40 | 240 días | 576000 | |
Duración de la Obra ….8 Meses | TOTAL(S/. ) | 737600 |
- ELEMENTOS ESTRUCTURALES:
- VOLUMEN EN ZAPATAS: ( L x A x H )x Z
Vz = (2.5m x 2.0m x 1.8m) 60 Z = 9 m3 x 60 = 540 m3
2.2 VOLUMEN DE COLUMNAS: ( L x A x H )x C
Vc = ( 0.4m x 0.5m x 17.55 )x 60 C = 3.51m3 x 60 = 210.6 m3[pic 2]
2.3 VOLUMEN DE VIGAS: ((L x A x H )x 5[pic 3]+(L x A x H )12 )x6
Vv = ((0.5m x 0.3m x 34)x 5 +(0.5m x 0.3m x 10m)x 12 )x6 (25.5m3 + 18m3)x6 = 261m3
Vol Total:
540m3 + 210.6m3 + 261m3 = 1011.6m3
...